9.2 Application of Post/Poll Rates

IEEE 2030.5 and, by extension, CSIP-AUS require the capability to remotely update the poll and post-rates for various resources. This functionality will be used by the SA Power Networks Utility Server to implementation to:

• Reduce DERControl poll-rates and measurement post-rates from the default of 5 minutes to minimise the on-site execution time for the Dynamic Exports capability test as described in Section 6;

• Increase measurement post-rates to minimise data traffic in periods of reduced distribution network risk.


Aggregator implementations utilising the subscription/notification function set will have an ability to receive notifications of control events on change.